Over Budget

A contractor in Atlanta tells a homeowner that rotted floor beams will add $7,500 to her kitchen remodel, and she wants proof before she agrees.

22 lines · Tap a line to hear it again

Dialogue

R

Rick Dalton:Morning, Mrs. Ford. Thanks for meeting me here so early. I wanted to show you this in person rather than over the phone.

M

Mrs. Alicia Ford:Your text said 'small problem, call me.' In my experience, Rick, nothing that starts with 'small problem' is ever small. What happened?

R

Rick Dalton:Fair enough. On Tuesday, when the guys pulled up the old tile and the subfloor under the sink, we found that three of the floor joists are rotted. Probably a slow leak from the old dishwasher, going on for years. You can push a screwdriver right into the wood here. Look.

M

Mrs. Alicia Ford:Oh my goodness. That's like a sponge. How did nobody notice this before?

R

Rick Dalton:It's a fair question. When I did the first walk-through in August, I went down into the crawl space, but the heating and cooling ductwork blocks that whole corner. I couldn't see it without taking the floor up.

M

Mrs. Alicia Ford:So what does this do to the budget? Be honest with me.

R

Rick Dalton:The repair adds seven thousand five hundred dollars to the job. That covers new joists, a new section of subfloor, the extra labor and the city inspection.

M

Mrs. Alicia Ford:Seven and a half thousand? Rick, the whole kitchen was supposed to be forty-two. That's almost twenty percent more. I have to be honest, it feels a little convenient that you find a big problem right after the walls are open and I can't exactly back out.

R

Rick Dalton:I understand why you'd feel that way, and I'd rather you ask than wonder. I'm not upselling you. That's why I took photos before we touched anything. I'll email them to you this afternoon, along with the measurements. And if you'd like a second opinion, I'll happily let another contractor come and look.

M

Mrs. Alicia Ford:I appreciate that. I would like the photos, yes. What are my options, realistically?

R

Rick Dalton:There are really two. The cheaper one is to sister the old joists, which means bolting new wood alongside them. That's about fifty-two hundred, and it works well when the rot is only on the surface. But in two of these, it goes almost all the way through. I wouldn't put your new stone countertops on top of that.

M

Mrs. Alicia Ford:And the second option is full replacement for seventy-five hundred.

R

Rick Dalton:Right. It's the one I recommend, and it's the one I'd do in my own house. The work itself takes about four days, but with the inspection we lose six working days in total.

M

Mrs. Alicia Ford:Six days? I'm hosting Thanksgiving for fourteen people. My mother-in-law is flying in from Phoenix. Please tell me I'll have a kitchen.

R

Rick Dalton:You'll have a kitchen. We were going to finish on November tenth. Now it'll be the nineteenth. The countertop company can move your delivery from the fourteenth to the seventeenth. That still leaves you a week before the turkey.

M

Mrs. Alicia Ford:That's tighter than I'd like, but okay. What about the money? I didn't plan for this.

R

Rick Dalton:Your contract has a contingency clause for hidden damage, so legally it's covered. But I don't want you to feel squeezed. How about half when we start and half after the inspection passes? And I'll take the three hundred and fifty dollar dumpster fee off the final bill for the delay.

M

Mrs. Alicia Ford:That's fair. Thank you. But I want all of it in writing before anyone picks up a hammer.

R

Rick Dalton:Absolutely. I'll write up a change order tonight with the price, the new dates and the payment plan. Nothing starts until you've signed it.

M

Mrs. Alicia Ford:Good. And Rick, I'm sorry if I sounded suspicious. My neighbor had a contractor who doubled his price halfway through, and it's made me nervous.

R

Rick Dalton:No apology needed. Asking questions is smart. Honestly, I'd rather have a client who reads every line than one who signs anything and gets angry later.

M

Mrs. Alicia Ford:Then you've got the right client. Send me those photos, and let's get this floor fixed.

Words in colour are explained in the glossary below.

Glossary

WordMeaning
subfloor/ˈsʌbflɔːr/the strong layer of wood under the top surface of a floor
joists/dʒɔɪsts/long pieces of wood or metal that hold up a floor
rotted/ˈrɑːtɪd/gone soft and broken because of water or age
crawl space/ˈkrɔːl speɪs/a low, empty area under a house, where you can only move on your hands and knees
ductwork/ˈdʌktwɝːk/the system of metal pipes that carries warm or cool air around a building
upselling/ˈʌpselɪŋ/trying to make a customer pay for more than they need
sister/ˈsɪstər/in building: fix a new piece of wood next to an old weak one to make it strong
contingency/kənˈtɪndʒənsi/a possible problem that you plan for in advance
change order/ˈtʃeɪndʒ ˌɔːrdər/a written agreement that changes the work or price in a building contract